Progress Report: Contract Programme 1

We are pleased to provide you with an update on the progress of Contract Programme 1, which is scheduled to be completed on Wednesday, June 28th. We value transparency and aim to keep the public informed about the project’s status. These works have been commissioned by Strutt & Parker, current Estate Managers, in collaboration with Wallace Stone, with works being carried out by Strath Civil Engineering. Here are the key highlights:

Overall Status:

Currently, we are facing a slight delay, approximately half a week behind the planned schedule. This setback is mainly attributed to the challenging nature of the sluice tunnel infill, which has proven to be more complex than initially anticipated. However, our dedicated team is working diligently to mitigate these challenges and ensure a successful completion.

Project Timeline:

We are currently in week 8 of the project, steadily advancing towards our goal. Despite the minor delay, significant progress has been made in various areas.

Completed Tasks:

Here are the notable accomplishments achieved so far:

Future Tasks (Next 4 Weeks):

In the upcoming weeks, we have planned the following activities:

We assure you that our team is committed to addressing the project challenges promptly and efficiently. We are working closely with stakeholders and relevant parties to ensure a successful and timely completion. Thank you for your patience and understanding as we strive to deliver a high-quality end result.


As you will notice, there are works being carried out down at the harbour!

The permanent works consist of: